Progress, photos and site logs
Record what was built, against which BOQ line, with photographic evidence. This is what substantiates a valuation and shortens the client query cycle.
Progress in Nuvailo is a quantity against a line, not a percentage someone estimated in a meeting. The project percentage is then derived, weighted by value, so a completed 40 percent of the value counts as 40 percent rather than 40 percent of the line count.
Recording progress
- 1
Pick the line
Search by code or description. Recently used lines appear first, because a crew usually works the same lines for days.
- 2
Enter quantity completed today
Cumulative is calculated for you. Entering today figure is less error-prone than maintaining a running total.
- 3
Attach photos
Taken in the app so they carry the date, project and line automatically.
- 4
Add a note if something is unusual
Weather stoppage, access blocked, an instruction received on site. These notes are what a delay claim is later built from.
Do not record progress beyond the line quantity. If more has been built than the BOQ allows, that is a variation, and it should be raised as one before it is claimed.
Photos that are worth having
- Take them in the app rather than the camera roll, so metadata and the line link are attached automatically.
- One wide shot for context, one close shot for the detail. Two photos per entry beats twenty per week in an album.
- Photograph problems immediately: damage, poor materials delivered, unsafe conditions. The date is the value.
- Photograph delivery dockets at the gate, not at the office three weeks later.
Using progress for valuations
At valuation time the quantities are already recorded per line with their dates, so the claim is a report rather than a reconstruction. When a client queries a line, open it and the evidence for those days is attached.
Firms that switch to logged progress usually report the same total value claimed but a shorter argument, because the query is answered in the meeting rather than a week later.